BROAD OAKUniversity of Bradford — Package 2

Four buildings.
One connected approach.

Broad Oak delivered a further heat-network retrofit across Horton A, Horton D, Pemberton and Ashfield, adapting four university buildings for district energy through coordinated mechanical, water-quality and controls upgrades.

Mechanical. Electrical. Renewable.Delivering nationwide
ProjectUniversity of Bradford — Package 2
ExpertiseHeat networks
SectorHigher education
LocationBradford, West Yorkshire
Buildings
Horton A · Horton D · Pemberton · Ashfield
Principal designer & contractor
1Energy
Network
Bradford Energy Network
01The challenge

The challenge.
Understood.

Four buildings with different heating arrangements required a building-by-building approach. The work had to address distribution, hydraulic control, hot water and underfloor heating while coordinating phased interfaces with the Bradford Energy Network.

Faculty of Health Studies, University of Bradford — campus exterior.
Faculty of Health Studies, University of Bradford — campus exterior.
02What we delivered

Expertise.
In every detail.

Our team upgraded pumps and control valves, installed filtration and air and dirt separation, and brought metering and water-quality monitoring into the heating circuits. At Horton, we added underfloor-heating minimum-flow protection and modified heating and hot-water services. At Pemberton, we converted selected areas from one-pipe to two-pipe distribution. Ashfield received pressure-independent radiator controls and point-of-use hot water. Working with 1Energy, we integrated the BMS and motor control centres, coordinated the phased network interfaces and completed commissioning, records and operating information across the four buildings.

  • Pump, control-valve and hydraulic circuit upgrades
  • Filtration, air and dirt separation, and water-quality monitoring
  • Pressure-independent radiator valves and differential-pressure controls
  • Selected one-pipe to two-pipe conversion at Pemberton
  • Underfloor-heating protection and revised hot-water provision
  • Phased network interfaces, in-house BMS integration and commissioning
03The result

The difference.
Delivered.

The completed works adapted four distinct heating installations for coordinated heat-network operation. Building-specific changes were brought together with controls, metering and commissioning, giving the university renewed infrastructure and the operating information needed to manage the transition to district energy.

4Campus buildings
3Plant-room control systems
2Pemberton work stages
BMSBuilding-wide integration
NEXTLet’s build what’s next

Your next project.
Our next conversation.

Let’s talk

Our accreditations

Quality. Safety. Professional standards.

  • ISO 14001 logo
  • ISO 9001 logo
  • Gas Safe Register logo
  • Constructionline logo
  • CHAS logo
  • NICEIC logo
  • HETAS logo
  • MCS logo

Choose whether this site can remember your featured projects. Your choice is kept for 90 days. You can change it using Cookie settings in the footer.

There are no analytics or advertising trackers on this site. Cookie policy · Privacy policy