Broad Oak delivered 291 kWp of rooftop solar across six buildings at UCA Farnham, combining tailored roof installations with a complete electrical and commissioning package for Corrigenda’s campus decarbonisation programme.

Mechanical. Electrical. Renewable.Delivering nationwide
ProjectUCA Farnham
ExpertiseSolar & renewables
SectorHigher education
LocationFarnham, Surrey
Client & principal contractor
Corrigenda
Programme
5 weeks · February–March 2025
Estimated project value
£340,700
01The challenge

The challenge.
Understood.

Six campus buildings, a mix of flat and slate roofs, and the need to respect the buildings’ appearance made this more than a standard rooftop installation. Each array needed the right mounting approach, safe access and well-considered connections to create a cohesive campus-wide system.

UCA Farnham — campus exterior and rooftop solar.
UCA Farnham — campus exterior and rooftop solar.
02What we delivered

Expertise.
In every detail.

Our team designed, supplied, installed and commissioned 481 Trina Solar Vertex N 605 W modules with 12 Fronius inverters across the six buildings. We used non-penetrative Renusol FS Pro E/W ballasted mounting on the flat roofs and Renusol Variosole+ mounting on the slate roof, matching each installation to its setting. Full roof edge protection, bespoke scaffold staircases and coordinated cable routes supported the five-week programme. Electrical connections, commissioning and Fronius Solar.web monitoring completed the package, bringing the individual roof arrays together with a clear view of system performance.

  • Complete solar PV delivery across six campus buildings
  • 481 Trina Solar modules with 12 Fronius inverters
  • Flat-roof and slate-roof mounting systems
  • Roof edge protection and bespoke scaffold access
  • Electrical connections and coordinated cable routes
  • Commissioning and Fronius Solar.web monitoring
03The result

The difference.
Delivered.

The completed installation gives UCA Farnham approximately 291 kWp of on-site renewable generation capacity. It adds a practical energy asset to the campus decarbonisation programme, with monitoring that lets the operator track performance across the systems as part of day-to-day energy management.

291kWp installed capacity
481Solar modules installed
6Campus buildings
5Week programme
NEXTLet’s build what’s next

Your next project.
Our next conversation.

Let’s talk

Our accreditations

Quality. Safety. Professional standards.

  • ISO 14001 logo
  • ISO 9001 logo
  • Gas Safe Register logo
  • Constructionline logo
  • CHAS logo
  • NICEIC logo
  • HETAS logo
  • MCS logo

Choose whether this site can remember your featured projects. Your choice is kept for 90 days. You can change it using Cookie settings in the footer.

There are no analytics or advertising trackers on this site. Cookie policy · Privacy policy