Broad Oak delivered a complete heating plant replacement at St Mary’s Church in Leamington Spa, combining 200 kW of new boiler capacity with upgraded circulation, controls and gas safety systems.

Mechanical. Electrical. Renewable.Delivering nationwide
ProjectSt Mary’s Church
ExpertiseMechanical & electrical
SectorFaith & community
LocationLeamington Spa, Warwickshire
01The challenge

The challenge.
Understood.

Replacing the church’s heating plant required more than a boiler change. Existing equipment and high-level heaters had to be removed, with the new installation integrated into the building’s services and the surrounding areas made good.

St Mary’s Church, Leamington Spa — exterior.
St Mary’s Church, Leamington Spa — exterior.
02What we delivered

Expertise.
In every detail.

We managed the complete changeover, removing redundant plant and high-level heaters before installing a new twin-boiler system. Two 100 kW Ideal commercial boilers now provide 200 kW of heating capacity, connected to the church’s heating circuits through renewed pumps, stainless pipework and a low-loss header.

Our in-house team delivered the flues, electrical installation and control panel alongside the S&S Northern gas safety system. We coordinated access, insulation and making good within the same programme, bringing every part of the replacement together for the church.

  • Twin 100 kW Ideal commercial boilers with new boiler pumps
  • Upgraded building circulation and expansion equipment
  • Stainless Mapress pipework and low-loss header
  • Commercial flues and coordinated high-level access
  • New control panel and integrated gas safety system
  • Electrical works, insulation, strip-out and making good
03The result

The difference.
Delivered.

St Mary’s now has a renewed commercial heating installation, with twin boilers, building circulation, controls and gas safety brought together as a complete system. Broad Oak delivered the mechanical and electrical works through one team, giving the church a single point of responsibility.

2New commercial boilers
100kW per boiler
200kW combined capacity
200L expansion vessel
NEXTLet’s build what’s next

Your next project.
Our next conversation.

Let’s talk

Our accreditations

Quality. Safety. Professional standards.

  • ISO 14001 logo
  • ISO 9001 logo
  • Gas Safe Register logo
  • Constructionline logo
  • CHAS logo
  • NICEIC logo
  • HETAS logo
  • MCS logo

Choose whether this site can remember your featured projects. Your choice is kept for 90 days. You can change it using Cookie settings in the footer.

There are no analytics or advertising trackers on this site. Cookie policy · Privacy policy