A new heating network.
Delivered in five weeks.
Broad Oak stripped out and replaced the heating network and radiators throughout Buxton Junior School in just five weeks, delivering a complete mechanical and electrical package during the summer break.
- Client
- Derbyshire County Council
- Principal designer
- Concertus
- Heating
- Existing heat pump with gas boiler backup
The challenge.
Understood.
The entire heating network and radiators had to be removed and replaced within the five-week summer break, ready for pupils and staff to return. The programme called for careful sequencing from strip-out through to commissioning, with the new distribution and emitters integrated with the school’s existing heat-pump-led system and gas boiler backup.

Expertise.
In every detail.
During the five-week summer break, our in-house team removed the old heating network and radiators and installed a complete new distribution system throughout the school. New pipework, valves, supports, insulation and protective boxing connected a full replacement package of panel radiators, low surface temperature units and fan convectors.
We delivered the associated electrical supplies, controls and wiring alongside making good and fire stopping, bringing every part of the new network together around the retained central plant. Flushing, water treatment, hydraulic balancing and commissioning completed the installation, followed by operating records and training for the school’s team. From strip-out to handover, the work was completed within the summer holiday window.
- Full strip-out of the existing heating network and radiators
- Complete new heating distribution throughout the school
- New panel radiators, low surface temperature units and fan convectors
- Integrated electrical supplies, controls and heating wiring
- Insulation, protective boxing, making good and fire stopping
- Flushing, balancing, commissioning and handover within the five-week summer break
The difference.
Delivered.
Buxton Junior School returned from the summer break to a completely renewed heating network and radiators, installed and commissioned in five weeks. The new distribution and emitters support the existing heat-pump-led system with gas boiler backup, with Broad Oak taking responsibility for the complete mechanical and electrical package from removal to handover.